| Establishing the NDA: the work continues | | Print | |
|
Setting up the Nuclear Decommissioning Authority (NDA) reflects a major shift in focus in Government policy for the nuclear industry. The priority is to provide strategic direction to the decommissioning and clean up of our £50 billion nuclear 'legacy.' Though important challenges will be faced during the next fourteen months, significant progress has been made towards achieving a fully operational NDA by April 2005.
The legislative process is now underway. The Energy Bill, introduced in the House of Lords, received Second Reading on 11 December and is now being considered in Lords Grand Committee (see page 7). Contracts and competition Initial responsibility for the management and operation of site licensees will remain with the incumbent site operators, BNFL and UKAEA. We need to negotiate and agree sensible timescales for the interim arrangements with incumbents that are fair but which do not impair the Government's goal of open and fair competition for site management contracts. It will be for the NDA to decide the timetable for introducing competition. Funding The opening balance of the NDFA will be credited with the value of BNFL's Nuclear Liabilities Investment Portfolio (NLIP), the Magnox Undertaking at the time it is extinguished and an additional sum provided by Government. The balance of the account will also be credited with revenues accrued from the NDA's commercial operations, including Magnox generation and THORP and SMP contracts. It will also reflect the annual contribution from Government. Mobilisation The appointment of the Chair, the non-executive Board members and the Chief Executive will go ahead as soon as possible after the Bill becomes law, to enable the NDA to begin recruiting its staff. LMU We now have initial, but comprehensive, plans presenting the scope of work, budgets and schedules needed to decommission and clean up sites. They provide essential 'road maps' for managing site activity under the new contracts. They also provide the raw data from which the NDA will prepare a UK-wide baseline to form the basis for its strategic planning and prioritisation. The work of constructing the baselines has been helped enormously by the assistance and cooperation of both the site operators and the regulators. The LMU has also been developing possible approaches to contracting for the NDA to consider. Much technical work lies ahead in finalising these arrangements. Once completed, they will provide important tools to enable the NDA to drive forward clean up of the nuclear legacy. Stakeholder engagement The project team's task is clear but challenging: to ensure that a viable Nuclear Decommissioning Authority is in place by April 2005. The Programme Board will see through the effective delivery of that objective. At our first meeting under my Chairmanship, we adopted the mission statement of ensuring that the NDA would have 'the best funding, the best policies and the best resources we could deliver.' That, of course, is where the challenge lies. |
|||
| < Prev | Next > |
|---|

